Turbine blade fails on Dogger Bank installation

Reports of the failure of a 107m long wind turbine blade during commissioning of the Dogger Bank wind farm – the world’s largest – have been confirmed by the operators. They remain tight- lipped, however, about any detail of the incident. The blade was built by GE Vernova, and is of the same design as the one that failed spectacularly in the Vineyard Wind development off the east coast of the USA in July, where thousands of sharp fragments of the blade washed up on nearby tourist beaches, leading to them being closed for several days during an emergency clean-up. Last week’s incident on the Dogger Bank was the third for this particular type of blade in three months. An earlier failure at the same site in May was, said GE Vernova at the time, ‘the result of an installation failure’. more, >>CLICK TO READ<< 10:44

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.