More Vineyard Wind blades must be removed, repaired
Vineyard Wind must remove an unknown number of blades that have already been installed south of Martha’s Vineyard while it repairs others, the company announced Wednesday. The project also received permission from the federal government this week to resume blade installation after it removes and repairs the components in the coming weeks. The latest announcement suggests investigations found more defective blades similar to the blade that failed in July and comes after the project quietly delivered at least four turbine blades from New Bedford to Cherbourg, France, where GE Vernova operates a blade manufacturing plant. >more, >>CLICK TO READ<< 11:48
Leave a Reply