Court challenge of test turbine could cost fishermen’s association
Fishermen who took the government to court may have to pay for it. Fundy Ocean Research Centre for Energy wants their legal costs to be paid by the Bay of Fundy Inshore Fishermen’s Association after a judge dismissed a judicial review the company was involved in. The review was requested after environment minister Margaret Miller’s decision last June to greenlight Cape Sharp’s turbine deployment in the Bay of Fundy. So far FORCE is the only respondent to follow Justice Robertson’s invitation to file for costs, made when she was making her ruling in early April after a full-day hearing in February. “We’ve been advised that Cape Sharp is not seeking its costs,” said the fishermen’s association’s lawyer, David Coles, in an interview Wednesday. But the provincial government is still unsure of what its position will be, he said. Click here to read the story 20:33